What is a critical-path method primarily used for?

  1. Estimating project costs

  2. Scheduling project timelines

  3. Hiring subcontractors

  4. Evaluating worker performance

The correct answer is: Scheduling project timelines

The critical-path method is fundamentally a project management technique used for scheduling project timelines. This method focuses on identifying the longest sequence of dependent tasks that dictate the minimum completion time for a project. By determining the critical path, project managers can understand which activities must be completed on time to prevent delays in the project schedule. This approach also helps in identifying tasks that have some flexibility in when they can be completed, allowing for optimization of resource allocation and better overall management of the project's timeline. It provides valuable insights into how changes to one part of the project can affect the entire schedule, thereby enabling more effective planning and execution. Other options, such as estimating project costs, hiring subcontractors, and evaluating worker performance, are important in their own rights but are not the primary focus of the critical-path method. Instead, they serve as separate aspects of project management that may require different tools and techniques.